Marine Works of Kharg Island NGL Recovery

For the export of Kharg NGL recovery plant liquid products, the design and construction of the jetty alongside export facilities was assigned to Omran Falat as an EPC contract. The jetty was designed for vessels up to 80,000 m3. In addition the seawater intake and outfall structures supply 50,000 m3 /h of seawater for Kharg NGL recovery plant cooling systems. The design and construction of seawater intake and out fall as well as the engineering and installation of related topside facilities and equipment.

Jetty

  • Location: Kharg Island
  • Overall length: 589 m
  • Access bridge length: 565 m
  • Platform width: 42 m
  • Pier water depth from MSL (Mean Sea Level): -16.3 m
  • Top of the deck from MSL: +10.0 m
  • Number of berthing dolphins: 4
  • Number of mooring dolphins: 6
  • Steel piles: 648 m of 2,200 mm dia. and 468 m of 2,000 mm dia. and 6,200 m of 1,100 mm dia.
  • Distance of external dolphins: 307 m
  • Onshore pipeline: 11,650 m of 100 mm dia. to 460 mm dia

Intake

  • Location: Kharg Island
  • Capacity: 50,000 m3 /h
  • Earthworks: 110,000 m3
  • Dredging: 34,000 m3
  • Subsea pipeline: 1,005 m of 2,200 mm dia.
  • Steelworks: 2,100 tons
  • Concrete: 8,500 m3
  • Onshore pipeline: 1,850 m of 2,200 mm dia.

Outfall

  • Location: Kharg Island
  • Capacity: 50,000 m3 /h
  • Earthworks: 60,000 m3
  • Dredging: 22,000 m3
  • Subsea pipeline: 305 m of 2,200 mm dia.
  • Steelworks: 600 tons
  • Concrete: 7,650 m3
  • Onshore pipeline: 150 m of 2,200 mm dia.